Overview

Placeholder text. An evaluation and retrofit of an existing school building identified as high seismic risk.

The challenge

Original drawings were incomplete, and all construction had to fit into summer breaks.

Approach

  • Ran a site investigation to confirm existing wall and diaphragm construction
  • Placed new braced frames to align with existing corridor walls and keep classrooms open
  • Designed new collectors to tie the diaphragm into the frames

Outcome

The building now meets the life-safety performance objective. It was completed across two summers with no loss of classroom days.

Photos